Quotes stop being comparable when each shop fills a different gap with a different assumption. This template closes the gaps.

Copy it into an email or a document. Nothing here is gated, tracked or emailed to you.

The template
SUBJECT: RFQ - [part name] - [your company] - [quantity]

1. PART
Part name and number:
Revision:
Files attached: STEP [yes/no]  PDF drawing [yes/no]  Other:
Part family: chamber / gas delivery / wafer handling / test or change kit / frame / spare
Overall size (mm):

2. MATERIAL
Material and temper:
Certificate required: mill certificate / none
Substitutions acceptable: yes / no

3. TOLERANCE AND FORM
Tightest linear tolerance:
Flatness / parallelism, with datum scheme:
Measurement condition: free state / constrained (state bolt pattern and torque)
Critical characteristics (list the features that matter):

4. SURFACE AND FINISH
Surface finish, by surface (Ra, with unit):
Finish type and thickness:
Masked features:
Rack mark restrictions:

5. CLEANLINESS AND PACKING
Cleaning level:
Packing: standard / degreased and double bagged / cleanroom packed
Handling restrictions:

6. INSPECTION AND DOCUMENTS
First article required: yes / no
Report scope: full layout / critical characteristics only / sampling
Reports per lot: yes / no
Certificates required: material / finish / heat treatment / weld

7. QUANTITY AND SCHEDULE
Quantity this order:
Repeat schedule (approximate is fine):
Needed by:
Spare / second piece wanted with this order: yes / no

8. COMMERCIAL
Delivery destination:
Incoterm:
NDA required before files are shared: yes / no
Quote validity requested:

9. QUOTE FORMAT REQUESTED
Please return these as separate lines:
unit price, setup or tooling, first article cost, finishing cost,
inspection cost, packing, lead time in working days, quote validity.

Why each block is there

  • 1. PartThe family narrows the supplier list faster than the drawing does. Say it explicitly.
  • 2. MaterialStating the certificate requirement up front is cheap. Adding it after delivery is impossible.
  • 3. ToleranceForm controls and the datum scheme, not just plus or minus. Say free state or constrained.
  • 4. FinishName the surfaces. A blanket note prices the whole part at the tightest number on it.
  • 5. PackingCleanroom packing is labour and consumables. Left unsaid, the cheapest quote is the one that assumed a cardboard box.
  • 6. InspectionFirst article plus sampling and a full report per piece are different prices and different schedules.
  • 7. ScheduleA stated repeat schedule usually prices better than the same quantity ordered lot by lot.
  • 8. CommercialDestination and Incoterm move the comparable price. Not every shop exports on its own documents.
  • 9. Quote formatSeparate lines are what let you see where a difference actually comes from.

The eight omissions that cost the most

Or send it to us once

Fill the form instead and we put the same information in front of up to 3 shops that fit the part. Reply within 24 business hours.